10 open problems across your jobs. Tap any one to act.
Pacific Heights Luxury Remodel
Marvin confirmed factory shift adds 9–14 days on the bay window order placed 2026-03-02.
What to do: Re-sequence interior trim ahead of glazing; lock alternate supplier for backup quote within 5 days.
SoMa Commercial Office Buildout
DBI requested updated egress calc for 14-room cluster. Currently 11 days into review (avg 14).
What to do: Schedule expediter call this week; pre-stage ceiling work that doesn't depend on revision.
Mission District Restaurant Renovation
Hood penetration counterflashing not yet installed. 0.8" rain expected Tue afternoon.
What to do: Install temporary peel-and-stick cap by EOD Mon; complete counterflashing Wed AM.
Vulcan range receipt $7,820 vs. estimate line $6,400. Likely model upgrade not flagged at PO.
What to do: Reconcile with kitchen consultant; charge variance to FF&E contingency if approved by owner.
Marin Custom Home Construction
Concrete trucks reporting rough ride; minor spalling at switchback. Risk of pump truck rollover.
What to do: Re-grade and add base rock before next major pour scheduled for next Thursday.
Oakland Multi-Family Development
City inspector booked out 6 days; podium pour planned next Tuesday for Bldg B.
What to do: Request priority inspection slot; pre-stage formwork strip on Bldg A to keep crews loaded.
AI photo review flagged under-torqued HDU8 anchors at gridlines 4 and 7.
What to do: Re-torque and re-photograph all HDU8 anchors before drywall covers walls.
Walnut Creek Medical Office Build
Electrical rough-in photo missing isolated ground bar landing — required for imaging suite.
What to do: Coordinate with electrician to land IG bar at MDP this week; resubmit photo before cover.
Union Square Retail Tenant Improvement
Terrazzo pour Day 1 today — full cure + grind + seal needs 7 days before fixtures.
What to do: Lock millwork install to T+8; tent and condition space to protect cure.
Hayward Warehouse Expansion
14 dock levelers shipped late from Rite-Hite; impacts only final commissioning.
What to do: Re-sequence striping and bumper install ahead of leveler set; no critical path impact.