Mission District Restaurant Renovation
Casa Lila Hospitality · Hospitality — Renovation
Restaurant rebuild: open kitchen, bar, 78 covers, full hood/MUA system, accessible restrooms, mural facade.
31% complete
Site photos & videos
Tap any photo to review, approve, or send back for fixes.
Problems (2)
Rain forecast Tue–Thu — roof open
HighHood penetration counterflashing not yet installed. 0.8" rain expected Tue afternoon.
Cost if ignored: $14.5k · Who: Renata Oliveira
Equipment receipt over budget line
MediumVulcan range receipt $7,820 vs. estimate line $6,400. Likely model upgrade not flagged at PO.
Cost if ignored: $4.2k · Who: Daniel Park
To-do (2)
Hood counterflashing complete
Roofing · Tom Reilly · due 1970-01-03
Grease interceptor city inspection
Plumbing · Aisha Bello · due 1970-01-05
Materials (2)
See all →Captive-Aire Type I hood 14ft
1 ea ·
Daltile Cementine porcelain
1,850 sqft ·